Location:

Oesede

Year under review:

2024/2025/2026/2027/2028

Processing status:

31.07.2025

Ongoing

Measure

Description of the measure

Origin of the measure

Investment

Realisation
planned
[Mo/year]

Responsible

Status

No.

Name

of the measure

Audit recommendation (A)

Cost

f. Realisation

Energy team meeting (T)

[€/a]

Project work (P)

Suggestion for improvement (V)

36

Realisation of PV systemInstallation of a PV system on the roof area H4a-13

P

900.000,€

10/2025

Electrics area

in progress

41

Lighting in halls 20, 21 and 22aSignificant improvement in workplace lighting

T

104.500,€

2025

Electrical systems

in progress

42

Lighting Hall 6b and 13Significant improvement in workplace lighting

T

approx. € 47,000

2026

Electrical systems

under review

 

 